Barilla Pasta Processing Plant

Order Year

10 March 2006

Location

Avon, New York, USA

Construction Started

June 2006

Completed

19 October 2007

Investment

$96.2m

Production

81,000t of pasta per year (2009)

Employees

140

Project Type

New pasta processing facility and distribution centre

Awards

'Design Build Institute of America Industrial Project Over $25 Million Merit Award' (2007), 'Food Engineering Magazine Food Plant of the Year' award (2008)

Contractors

Faithful+Gould, TranSystems, Whiting-Turner, M/E Engineering, BME Associates

Suppliers

Rockwell Automation, Ricciarelli, Zucchini, Brambati S.p.A., Logiflex, Philips, Cooper Lighting, Carlisle SynTec
Expand

Free download worth over $5000
Download our 2019 Technology, Media and Telecoms Predictions Report

Worth up to $5,850

In this report, we look at the 30 big tech themes for 2019, identifying winners and losers for each theme. This report will impact all industries helping:

  • CEOs/Senior Staff: in all industries understand the disruptive threats to their competitive landscape
  • Investors: Helps fund managers focus their time on the most interesting investment opportunities in global TM
Close
Close
Close